Highview Condominium II The eleventh regular meeting of the 2004-2005 Highview II Board of Directors
was called to order at approximately 7:45 p.m. by Marjorie Cannon, Vice
President. Board members in attendance: Miriam Biren, Sanchie Bobrow , Robert Boynton,
Marjorie Cannon, and Richard Re. Board members absent: Victor Bellini, Stefanie
Greenberg, Tamara Keshecki, and Frank Mattera. Bellini’s proxy to Boynton,
Keshecki’s proxy to Bobrow. Jennifer Ogman attended from J.A.L. Diversified
Management. 1) Minutes of the July 13, 2005 meeting were distributed. Approval of the
July minutes was tabled in order for the meeting to move to critical business. 2) Roof replacement project – updates since regular meeting on the
full-Board in July: a) Unit owner authorization for a building loan: On August 10, 2005,
a Town Meeting was held for the purpose of discussing building loan. In order
for the Highview II Board of Directors to take out a loan on behalf of the
building, Bylaws require an approval by a simple majority of all owners
(majority of unit points). It was confirmed with the Board’s attorney,
Michael Swaaley, that the Bylaws do not require a super majority (two-thirds)
for this action. Unlike the business of the Annual Meeting, this type of vote
would not be limited to those unit owners attending a meeting and no proxies
would be involved. In advance of the meeting, Highview Treasurer Rich Re distributed
information to all owners concerning the building’s options for paying for
the necessary repairs including single cash payment, loan options, and/or
Special Assessment. The mailing included a form for owners to authorize or
reject the loan. Owners could either mail the form in or decide after
attending the Town Meeting. At the August 10, 2005 Town Meeting, there was discussion of the loan
options and the nature of the required building repairs. Additional discussion
involved concerns raised by several unit owners about the previous roof
installation (approximately eight years ago), whether any current board
members were on the board at the time (none of the current board members were
serving) and whether legal action had been considered against any or all of
the involved parties (yes, it had been considered). Owners were encouraged to
read the current board’s February 9, 2005 meeting minutes that summarize
Becht Engineering’s Phase-1 investigation report (commissioned fall 2004)
which included an
Board of Directors - Meeting Minutes
September 14, 2005, 7:30 p.m.
evaluation of the
possibility of suing either the previous installer and/or managing agent at
the time of the previous roof installation. The building’s attorney was also
asked to advise on the possibility of legal suits
– against the roof coating provider (Firestone), the installer (Mill Basin
Roofing), and/or the managing agent (Finnerty Management). But the roof
coating itself did not fail (which is what Firestone’s warranty provided)
and no professional engineering services seem to have been involved with the
project. As to whatever professional advice Finnerty Management may have
provided the board at the time, the only documents that the current board has
found from Finnerty Management to that board indicate that the work was
progressing, but make no mention of any concerns. Once again, it was noted
that none of the Board’s current members were on the board at the time of
the previous roof project.
For the large sum of money being requested at this time, there was a question about how the current roof problem was investigated, how solutions were determined, and how the project was bid. In reply, it was noted that there were five bids received for the selection of an engineering firm and an equal number for the roofing work itself. The board typically requests three competitive bids for any major project and at the time of selection a board vote is recorded and included in the meeting’s minutes. The previous year’s Board minutes provide substantial detail about the process and board deliberations in determining the current approximate $300,000 in repairs. It was also suggested that residents should review the Capital Reserve Study of two years ago which details the major capital repairs and costs owners should anticipate and consider saving for over the next 15 years.
At the Town Meeting’s conclusion, completed authorization ballots were submitted by owners (in addition to those previously submitted by mail) and a tally was taken. The tally indicated thirty-eight (38) owners representing 56.69% of all unit points had voted to authorize the loan. Exceeding the 50% of unit points required, it was announced that the loan had been authorized.
The tally taken at the meeting indicated a total of seven (7) unit owners representing 11.1002% of all unit points voting against any loan and twenty-two (22) unit owners representing the remaining 32.2098% of all unit points had not responded to the authorization request ballot. (Per the attached summary of this authorization distributed to unit owners, 58% of unit points were ultimately accounted for in favor of the authorization.
b) Clarification votes taken by the Board relating to the proposed loan: Per a unanimous vote of the eight Board members present at special meeting on August 8, 2005 (Biren, Bobrow, Boynton, Cannon, Greenberg, Keshecki, Mattera, and Re), unit owners not participating in the loan have until September 21, 2005 to submit their entire share of the $300,000 required by the building. A second unanimous vote was taken at the same time and all unit owners choosing to pay their total share up-front are exempted from any and all costs related to the loan. All loan costs will be limited to and shared by the individual unit owners actively participating in either of the loan’s two options.
c) Loan closing: Ogman indicated that closing is expected either next week or last week of September. Any owner who has not submitted their total share will automatically be included in at least the first year of the loan (during which time the monthly addition to their common charge bill will be approximately $30, varying according to unit points). After the first year, loan participants may pay their remaining share of loan costs or by not doing so thereby commit to the remaining five full additional years (estimated to be approximately $100 per month, but subject to the actual numbers). There is no option for a unit owner to pay off their share at any time other than as the three options that were initially offered to all unit owners and discussed at the Town Meeting.
d) Next steps of roof project:
i) HVAC work: Although no HVAC bid was approved at this meeting, the Board voted its "intention" to arrive at a contract with Fahrenheit HVAC, Ltd. Prior to Board approval, Fahrenheit will have to add wording in their contract to guarantee a performance outcome of the exhaust system relative to each apartment’s vents. Their current contract bid offers no formal assurance that the equipment they are installing will successfully ventilate the building and similarly provides no indication of what situation they had found to correct. Ogman will have contractor revise bid accordingly and forward to Board for an approval.
Since the contractor made no statement in his contract as to what the problem was that was being fixed, would not be connecting the fans to an electrical source at completion of the project, and up to this point had made no commitment of a performance outcome, Boynton requested that the vendor also "prove" a currently inoperable line prior to the board even signing the revised contract, in order to provide the board with a sense of Fahrenheit HVAC’s comprehensive understanding of the problem. Ogman will schedule a single-line (A-line kitchen) test with the contractor. (The A-line was chosen since the line exhibits no intake draft whatsoever when the roof fan is running.)
ii) Electrical contractor: Since Fahrenheit HVAC’s bid specifically states that they will not connect the new units to electrical, bids will be required by the board from electrical contractors to hook up the fans. Ogman will get the multiple bids for Board review. The Board will need to approve an electrical contractor in time for participation in the pre-construction meeting.
iii) Pre-Construction meetings: Ogman reported that she had a pre-construction meeting with Board President Stefanie Greenberg, S&S Roofing, and Fahrenheit HVAC. S&S and Fahrenheit HVAC were prepared to start the project in mid-October. The Board questioned why Becht Engineering had not participated, since they were being paid to schedule S&S and oversee all of the S&S work on a full-time basis to completion. Ogman suggested that Becht had not expressed interest in participating. Ogman was asked whether the Phase-3 contract with Becht (approved at the June board meeting on June 8th and re-affirmed with JAL on June 22nd) had been signed by Greenberg, forwarded to Becht, and the required $10,000 retainer fee paid by JAL. Ogman indicated that none of these actions had taken place and it was her understanding that the Board president had decided to not have Becht Engineering supervise the job at all. This was the Board’s first indication of the three month delay and it was noted that Ogman had been repeatedly asked about Becht’s scheduling by Board members without ever being told by Ogman that the contract was not in place as had been voted.
Noting that the Phase-3 $22,540 contract with Becht had been approved in June by eight individual board members (with Greenberg voting against Becht and instead voting to have JAL Management oversee the construction), the board voted to have the Secretary (Boynton) sign the contract without delay and for JAL to make the $10,000 retainer payment to Becht Engineering.
iv) Since Becht had not been included in the process for three months (June-September), there was some question about the timing of remaining steps and what delays in completion may have been created. During the last three months, Becht was to have been working with the building’s attorney to devise a contract-draft which according to Becht was to have been presented to S&S prior to the scheduling any pre-construction meeting.. Although Ogman indicated this process of negotiation and meetings would conclude in a matter of days, the board questioned this schedule noting that the process recommended in the spring by Becht and reflected in prior board minutes indicated that a contract draft should be created and reviewed by Swaaley and Becht, presented to S&S for their review, a pre-construction meeting scheduled, possible revisions to the contract at the pre-construction meeting, review again by Becht, Swaaley and S&S, and only then would the contract come to the point of being signed by the Board.
The Board questioned how all these meetings, negotiations, and agreements would conclude within 1-2 weeks, while on the date of this meeting the building had no agreement in place with the engineering firm (Becht) that was to oversee this process and that apparently there had been no indication by JAL to Becht that Highview had any intention of using their services in the construction phase of this project.
v) Summarizing next steps:
- Becht to receive signed contract and retainer;
- contract draft prepared for S&S after review by Swaaley and Becht;
- pre-construction meeting with contract draft;
- review, possible revisions of contract draft, and Swaaley/Becht/S&S approvals of roofing contract;
- board approval and Swaaley review of contract for HVAC work;
- bids, board approval, and contract for HVAC electrical work;
- loan closes and funds become available for contractor payments;
- roof project is conducted and completed as payments are made.
5) Repairs and maintenance:
a) There was discussion of the painting of all unit doors. In review, the board discussed how the painting was initially schedule in December 2004 and how at each monthly meeting since then Ogman has reported that the super would be doing the job in the coming weeks.
At more than one board meeting during this lengthy period, the managing agent indicated that a memo had just been distributed to unit owners (reminding each unit owner that they would need to open their door in order for the edges to be painted). However, board members questioned the distribution of this memo to all residents since no board member had received the memo.
Ogman suggested that the project be completed in October since it is too hot to work in the hallways at this time. The Board agreed. Ogman will confirm that the correct finish of paint is used to assure easy cleaning. With the confusion over this project and the need to open each unit door to complete the job, the board requested that each unit owner sign a roster as their unit door is completed. It was suggested that this might be combined with smoke detector battery replacement by the super, which is to be completed by the super at no charge to residents every spring and fall.
b) No estimate was available from Christie Garage Door for the timer linked to the garage door motor has to be estimated. This estimate was previously requested of Ogman at the March, April, May, June, and July meetings.
c) There was no update concerning the condition of the garage maintenance items discussed at the May, June, and other previous meetings.
d) Plumbing repairs: The pressure valve on the water main has been added, reducing the building’s water pressure from 180 lbs. to the recommended 80 lbs. There was discussion about complaints of low water pressure in various units. Ogman indicated that RSK Plumbing would be adjusting the system within the week. Ogman was asked to have a gauge installed at the valve, noting that since it is an adjustable pressure valve a monitoring gauge would assure that it is performing properly. Ogman agreed and indicated that the addition of a gauge had already been requested by JAL and was to be installed later in the week.
Ogman was asked when the other approved plumbing work (hot and cold riser valve replacement, gas riser valve locating, and hot water service line replacement) would begin and there was concern for not having the lobby ceiling back together and major water service interruptions over prior to the holiday season.
e) There was discussion of JAL’s building maintenance responsibilities. There was discussion of the Maintenance Committee, approved by the Board on August 15, 2005 (Boynton, Bellini, Bobrow, and proxies from Keshecki and Mattera). The approval included the appointment of Nora Colford and Anna Civitano as non-Board committee members. Ogman reported that her ongoing weekly meetings with Anna Civitano are productive. The Board observed and discussed examples within the lobby area of long-term accumulation of dirt, grease, and coffee spill stains on a wall. A copy of the building’s maintenance requirements was discussed in order to confirm JAL’s commitments to Highview II. The Board requested that Ogman continue to include copies of her weekly maintenance reports in the management package distributed at board meetings by JAL. .
Meeting was adjourned at approximately 9:30 p.m.
Robert Boynton, Secretary
Attachment:
Highview Condominium II
Thanks to all who participated in our Town Hall meeting on Wednesday, August 10, 2005. As you know, the main focus of our meeting was to discuss several major repairs that the building requires and to vote on how to fund those repairs.
The ballots were counted at the end of the meeting and the board received approval from 58% of building residents authorizing a loan in the amount of $300,000 to fund the below listed repairs:
Total $300,000
The terms of the loan are as follows:
Since the loan has been approved, residents can choose from the following three payment options:
Option 1 – Non Participation – Residents can pay their share of the repair cost up front and not participate in any phase of the loan. Residents that choose this option will not be responsible for any of the closing costs associated with the loan. A list of actual amounts due for each unit, based on each unit’s percent of common interest, is attached to this letter. If, after the completion of repairs, the total amount required to complete those repairs is less than $300,000, residents that selected this option will be refunded any unused portion of their payment. If you select this option, payments must be received on or before September 21, 2005.
Option 2 – Partial Participation – Residents may participate in the first year, interest only, portion of the loan and pay their share of the repair cost prior to the start of the 5 year loan period (payment will be due approximately 11 months after the inception of the loan). The actual amount due at that point will be communicated to you once all listed repairs have been completed and final repair costs and closing costs have been calculated.
Option 3 – Full Participation - Fully participate in the loan for the 1 year, interest only, period and the 5 year Self-Amortizing Loan period.
If you choose Option 1, please detach the below form, find the amount due for your unit number on the attached list, attach a check for the correct amount payable to Highview Condominium II, and mail your check and form to:
Highview Condominium II - c/o JAL Diversified Management Corp.
PO Box 9020
Hicksville, NY 11802-9020
To participate in this option your check must be received by the cutoff date of September 21, 2005.
If you choose Option 2 or 3, no action is required at this time. Your first "interest only" payment will be incorporated into your Highview II common charge bill from JAL, beginning with the October 1, 2005 bill.
Sincerely,
Highview Condominium II Board of Managers
Name___________________________________________________________________
Apartment Number________________ Amount Due: ________________________
I/We accept Option #1, and have attached a check for the entire amount due for my unit based on the attached list.
Signature_______________________________________________________________