Highview Condominium II The ninth regular meeting of the 2004-2005 Highview II Board of Directors was
called to order at 8:00 p.m. by Marjorie Cannon, Vice President. Board members in attendance: Victor Bellini, Sanchie Bobrow, Robert Boynton,
Marjorie Cannon, Tamara Keshecki, and Richard Re. Board members absent were
Miriam Biren, Stefanie Greenberg, and Frank Mattera. Stefanie Greenberg was
represented by proxy to Richard Re and Miriam Biren was represented by proxy to
Sanchie Bobrow. Russell Fernandes, (Principal/Vice President) attended from
Becht Engineering. No representative was present from J.A.L. Diversified
Management. 1) Discussion of roof replacement project with Becht Engineering
representative Russell Fernandes. a) The individual contractor bids were discussed, including cost per foot
bids for additional work that might be required, reputation of contractor,
ability to complete the job in a timely fashion, and how the work would be
performed. Only as much of the old roof would be torn up on any day as the
contractor could complete with a base layer by the end of the day. In discussion of engineering oversight options for the project: since the
roof has a wooden instead of concrete base, problems are likely to be
localized and not equally continuous throughout the entire roof’s
sub-structure. Since a new section is torn up and finished by the end of each
day, whatever structural problems exist in a particular section will only be
visible to the crew working that day. Unless the particular problem happens to
be visible on the day and time the engineer stops by, it is left to the work
crew to identify structural problems rather than the engineer. If a roofer
sees it in their best interest to finish the project and not pursue
complicated structural repairs, no one assumes any liability for pursing the
problem unless the engineer is present. For this reason, Becht recommended
full-time daily inspection of the work, instead of a limited four 4-5 hour
visits to the project. The question of asbestos removal was discussed. Preliminary inspection by
Becht found no asbestos, however Fernandes indicated that if asbestos was
found during course of the project, additional bids from an environmental
contractor for proper removal and disposal would be required, perhaps adding
as much as $40,000 -$50, 000 to the project. If this analysis has not been
performed, it was noted that the Board’s Phase-1 approval in November
authorized any asbestos testing as determined necessary by Becht to be
performed "at cost". Becht will confirm status of this review. It was discussed with Fernandes that S&S Roofing had been selected by
all Board members who had voted. Votes were still outstanding from Greenberg
and Mattera. b) After Becht departed, a vote was taken to determine which Phase-3 would
be accepted. Bellini, Boynton, Bobrow, and Cannon voted in favor of Phase-3
Option A at $22,540. Re requested addition time to consider his vote. As a
critical vote of the Board, although only 5 votes would be necessary for
action, it was agreed that votes of all nine Board members should be recorded.
Similarly, it would be preferable for the votes currently available by proxy
to be confirmed by the individual Board members. c) There was discussion of the proposed loan. Rich Re confirmed that a
second 5-year, fixed-rate bank was available for comparison. However, the
institution had not provided all of the final costs for a direct comparison to
the first bank. Information will be provided shortly. d) There was additional discussion of the other capital repairs that need
to be covered by this loan to avoid a Special Assessment later in the year.
Competing bids to be coordinated by JAL were not available at this meeting. e) Reviewing remaining steps in the process: 1) complete Board votes for
roof contractor, 2) complete Board vote for Phase-3 option and sign contract,
3) determine cost and approve individual bids for the Capital Repairs to be
completed this year within scope of loan, 4) determine best loan based on
total, 5) schedule and conduct Town Meeting to review loan options, 6) vote by
all unit owners (including those not at this meeting) to achieve the 50%+
necessary to authorize a building loan, 7) sign loan application and seek bank
approval, 8) sign roofing and other contracts, and 9) have projects performed. 5) Repairs and maintenance: a) There was no update concerning the painting of all unit doors
that was scheduled to begin a couple months ago. A copy of the June 7th
memo was included in this month’s management report, however Board members
(and therefore probably all unit owners) have not received it otherwise. b) No estimate was available from Christie Garage Door for the timer
linked to the garage door motor has to be estimated. This estimate was
requested of Ogman at the March meeting and mentioned again at the April and
May meetings. c) Repair and replacement costs for the exhaust fan roof top system
will be estimated in June. d) There was no update concerning the condition of the garage and
maintenance items discussed at the May meeting. e) Both air conditioners in the super’s apartment have failed. The Board
approved replacement of the original (20+ year old) installation in one room.
The one replaced only a couple years ago should have a firm estimate of repair
costs before replacement is considered. Boynton was authorized to make this
determination with JAL. f) Other unapproved repairs have been tabled pending loan discussion. Meeting was adjourned at approximately 10:00 p.m. Robert Boynton, Secretary
Board of Directors - Meeting Minutes
June 8, 2005, 7:30 p.m.