Highview Condominium II The seventeenth meeting of the 2004-2005 Highview II Board of Directors was
called to order at 8:15 p.m. by Richard Re, President. Board members in
attendance: Victor Bellini, Robert Boynton, Marjorie Cannon, and Richard Re.
Miriam Biren was absent, but represented by proxy in order to achieve a quorum
for the meeting. Board members absent: Stefanie Greenberg, Tamara Keshecki, Al
Lamoglia, and Frank Mattera. Irwin Chopak attended from J.A.L. Diversified
Management. 1) Roof rebuild update & tour: The board made a tour of the roof
with Irwin Chopak and a representative of S&S roofing in advance of the
meeting. Approximately ¼ of the roof has been replaced and no structural
repairs were required in that area. 2) Minutes: Minutes of the March 14, 2006 board meeting were approved. 3) Building Maintenance & Repairs: a) Irwin Chopak indicated dissatisfaction with the super’s performance in
maintenance of the building over the past six months. The super had been due
for his annual evaluation in October, however the evaluation had coincided
with a management transition to Irwin Chopak and Chopak requested that the
evaluation be delayed for six months in order for him to become more familiar
with the super’s performance. There was a discussion of particular situations. Chopak indicated specific
maintenance requests he had made to the super which had been repeatedly
ignored. Specific situations included the elevator floor which is supposed to
be waxed every two weeks but had not been waxed in three months, the compactor
room’s complete weekly wash out with a hose which had not been performed in
at least six months, and the parking garage’s monthly wash-out which had not
been performed since August 2005. Each item was discussed relative to the
regular maintenance schedule and the frequency of completion as specified in
the written description received by the super when he was hired and reviewed
annually as part of his annual evaluation. Chopak indicated his intention to formally warn the super of unsatisfactory
performance and advise the super that his performance would need to improve
within 60 days. Chopak requested the Board’s support in this matter and it
was so voted. b) Sidewalk lighting: Chopak indicated that the lighting fixtures
are worn out. At least four of them have been broken off at ground level by
vandalism. Board members commented that they had been replaced within the past
two years with fixtures selected by JAL. Chopak indicated a fix. The board
approved. c) Garbage chute handles: In response to a handle falling off a
garbage chute door, Chopak recommended replacing all of the handles with a
different type of handle. The board approved. d) Laundry room table: Chopak indicated that he was unable to get
anyone to fix the laundry room table base. He recommended replacement of the
base. The board tentatively approved pending review of estimates and a board
approval by email. e) Laundry room ceramic tile: The board approved removal and
replacement of the tile around the washing machine base. Although too late to
revisit the decision, concern was expressed that the original problems with
the tile was due to an expansion of the slab performed by CoinMach to support
new larger machines and that the board had discussed holding CoinMach
responsible for the repair. At that time, JAL indicated that the repair could
easily be completed by the super and CoinMach was not approached about the
repair. Chopak will offer bids for board approval. This will be completed by
an email vote. f) Painting & smoke detector battery replacement: Four unit
doors remain unpainted and there is no record of which smoke detector
batteries were replaced. It was discussed that the super should be changing
smoke all unit detector batteries this month per building spring/fall policy.
The Board secretary will supply Chopak with an Excel format chart for the
super to use in documenting completion. g) Elevator’s mechanical systems: At the January board meeting,
there was discussion of the elevator’s overall condition, a vibrating sound
residents have recently complained about, and the nature of repairs in the
last year. At that time, Chopak recommended bidding for an analysis and report
of the system’s condition independent of the current elevator maintenance
contractor. Chopak indicated at the March meeting that he was only able to
locate one contractor who does this type of work. As of this April meeting, no
bids were available and no other contractors have been located to offer a bid
for the service. h) Verizon terminal box: At the January board meeting, Irwin updated
the board on the Verizon terminal box issue and indicated that Verizon is
interested in further discussion of replacing the box with an updated system.
Chopak repored that he has met with Verizon and they will be replacing the
building’s terminal box with a digital system. i) Video security system: As a follow-up to the February and March
board meetings, Chopak was reminded to order new video tapes from Alarmingly
Affordable. j) Building super’s hours: As a follow-up to the February and
March board meetings, Chopak was reminded to post the super’s regular work
hours. As a follow-up to the February and March board meetings, Chopak was
reminded to speak with the super about posting, as required in the super’s
job description, his return time whenever the super will be away from the
building during normal working hours. k) Emergency contact names and telephone numbers: As a follow-up to
the February and March meeting, Chopak was reminded to update the contact
information on the office door, noting that Stefanie Greenberg’s and
Jennifer Ogman’s names and numbers were still listed while Irwin Chopak’s
contact information was not listed. 4) Capital Repairs update: a) Exhaust fan repairs: Becht Engineering has completed their
evaluation of the exhaust fan system. i) Becht’s April 4, 2006 report indicated that all 15 fan units have
reached the end of their useful lives. Blockages were found in six of the
fifteen lines. The wooden decks and masonry shafts of four lines had collapsed
near the roof and require repairs that can be completed as the roof is being
rebuilt. All lines were video’ed as part of the investigation and there are
13 videos on file. ii) Chutemaster, chimney sweeps, and boiler cleaning services will be asked
to submit bids on the duct blockage repairs. iii) Becht has provided a spec. sheet list with performance requirements
for each of the fifteen fans. Comparative bids will be developed for the fan
units per Becht’s specification. b) Bulkhead storage: At the March meeting, there was discussion of
the lawn furniture stored in the chimney bulkhead. The board voted to dispose
of the furniture and Chopak was to have the super move the lawn furniture from
bulkhead to curb for disposal before the roof work begins and any other
bulkhead storage was to be moved to the locked storage room inside the parking
garage. The status of this situation was not confirmed at this meeting. c) Summarizing next steps with roof: d) Riser valves and water service line replacement update: Finishing
work has continued on the lobby ceiling into April. It is anticipated that the
project will be completed by this Friday. The board indicated to Chopak that
this contractor will not be approved for any additional/future projects. e) Fire escape restoration and painting: Fire escape painting has
begun. The board requested clarification from Chopak about the primer and two
coats of paint that were to be completed by the contractor. Chopak explained
that the paint contained a primer and that the coat coats of paint were
completed at the same time by multiple brush strokes. f) Sprinkler heads: Per discussion at previous board meetings, an
additional sprinkler head was required at the other end the recycling area.
Chopak reported at this meeting that the spray from the one sprinkler head
would reach the entire area and no additional heads are needed. 5) Financial report: The board approved the FY2005 audit. 6) Legal issues: a) Cable installation: Irwin Chopak indicated that rather than
approach the unit owners for improper installations, he will approach the
Cable company for corrective action and report back at the next meeting. b) Annual window guard notice distribution: The annual January
Window Guard notice has been completed. c) Driveway parking: Irwin Chopak was to report back at the March
meeting with a new towing contractor and signage changes to reflect the new
towing contractor. No update was available at that time. Chopak reported at
the April meeting that he is unfamiliar with any towing services on Staten
Island, but will speak with Jennifer Ogman for a recommendation. d) Shrubbery damage: There was no update on the shrubbery damage
caused by the snow plow contractor. Irwin indicated that the snow plow
contractor will not be paid until the situation is resolved. Chopak was asked
by the board if he had discussed the situation with the contractor and he had
not. Irwin was asked if the contractor had submitted a bill. Irwin said he had
not. The meeting was adjourned at approximately 9:30 p.m. Robert Boynton, Secretary
Board of Directors - Meeting Minutes
April 11, 2006, 7:30 p.m.